Article 23

Decision-making powers

1. The transmission system operator shall establish and pub­ lish transparent and efficient procedures for non-discriminatory connection of new power plants to the transmission system. Those procedures shall be subject to the approval of national regulatory authorities.

2. The transmission system operator shall not be entitled to refuse the connection of a new power plant on the grounds of possible future limitations to available network capacities, such as congestion in distant parts of the transmission system. The trans­ mission system operator shall supply necessary information.

3. The transmission system operator shall not be entitled to refuse a new connection point, on the ground that it will lead to additional costs linked with necessary capacity increase of system elements in the close-up range to the connection point.